| Rapid Plans Company | ||||||||
| (512) 467-6544 (Office) (512) 467-6533 (Fax) | ||||||||
| txdot@rapidplans.com | ||||||||
| Sep-12 | Letting | Current As Of: | September 14, 2012 | 10:39 AM | ||||
| STATUS | COUNTY | PROJECT NO | CSJ | HWY | EST COST | PRIOR LETT | DAY | |
| Released | Anderson | NH 2008(510) | 0205-07-043 | US 79 | $42,809,367.00 | 1 | ||
| Released | Austin | BR 2008(612) | 0913-20-079 | CR | $200,110.42 | 1 | ||
| Released | Bastrop | STP 2013(025)HES | 0807-05-019 | FM 535 | $3,983,035.96 | 1 | ||
| Released | Bell | NH 2012(691) | 0015-14-091 | IH 35 | $201,162,553.38 | 1 | ||
| Released | Bell | STP 2013(016)HES | 1308-01-029 | FM 1123 | $4,453,101.38 | 2 | ||
| Released | Bexar | BR 2013(030) | 0017-02-075 | IH 35 | $5,715,297.58 | 2 | ||
| Released | Bexar | STP 2013(033) | 0465-02-024 | FM 1518 | $1,078,121.37 | 2 | ||
| Released | Bexar | STP 2012(617)SB | 2452-01-051 | LP 1604 | $10,470,746.58 | 1 | ||
| Released | Bowie | NH 2013(051) | 0217-02-030 | US 71 | $395,445.00 | 1 | ||
| Released | Cameron | STP 2012(116) | 0327-08-084 | BU 77-X | $2,281,684.73 | 1 | ||
| Released | Cameron | STP 2013(042) | 0872-04-026 | FM 506 | $5,326,611.00 | 1 | ||
| Released | Cameron | STP 1102(184)SRS | 0921-06-242 | CS | $213,298.60 | 1 | ||
| Released | Cameron | STP 1102(185)SRS | 0921-06-247 | CS | $599,549.60 | 2 | ||
| Released | Collin | STP 2013(010) | 2351-01-019 | FM 2478 | $190,000.00 | 1 | ||
| OFF | Collinsworth | STP 2013(137) | 0031-04-050 | US 83 | -$86,028.00 | |||
| OFF | Cottle | STP 2013(136) | 0032-02-032 | US 62 | -$24,983.00 | |||
| Released | Dallas | IM 0356(436) | 0196-03-257 | IH 35E | $430,388.00 | 1 | ||
| Released | Dallas | NH 2013(009) | 0353-04-093 | SP 348 | $100,000.00 | 2 | ||
| Released | Dallas | STP 2013(139) | 1047-03-064 | FM 1382 | $607,442.00 | 2 | ||
| Released | DeWitt | STP 2013(072) | 0270-01-049 | SH 72 | $2,500,000.00 | 2 | ||
| Released | Eastland | STP 2013(080)HES | 0007-03-086 | IH 20 | $1,714,015.50 | 1 | ||
| Released | El Paso | NH 2013(043) | 0001-01-054 | SH 20 | $4,133,007.84 | 1 | ||
| Released | El Paso | STP 2013(044)MM | 0167-01-107 | US 54 | $1,500,000.00 | 1 | ||
| Released | El Paso | NH 2013(045) | 0924-06-377 | VA | $500,000.00 | 2 | ||
| Released | El Paso | STP 2013(046) | 0924-06-415 | VA | $1,710,756.60 | 2 | ||
| Released | El Paso | IM 0101(263) | 2121-03-142 | IH 10 | $3,333,995.00 | 2 | ||
| Released | El Paso | CM 2013(048) | 3592-01-006 | SH 178 | $1,896,032.00 | 2 | ||
| Released | El Paso | STP 2009(791) | 8056-24-001 | MH | $6,450,193.92 | 1 | ||
| OFF | Floyd | STP 2013(015) | 0740-02-028 | FM 97 | -$1,902,627.80 | 1 | ||
| Released | Freestone | STP 2013(056) | 0166-02-041 | SH 75 | $6,201,601.70 | 1 | ||
| Released | Gillespie | STP 2013(028)HES | 1135-01-026 | RM 783 | $3,571,018.33 | 1 | ||
| Released | Gillespie | STP 2013(029)HES | 2719-01-008 | RM 2721 | $2,902,700.00 | 2 | ||
| Released | Goliad | NH 2012(532) | 0088-02-056 | US 59 | $1,815,642.59 | 2 | ||
| Released | Grayson | STP 2013(069) | 0410-02-030 | US 69 | $4,865,550.58 | 2 | ||
| Released | Grimes | STP 2013(058)SB | 0338-01-054 | SH 105 | $7,327,150.50 | 2 | ||
| Released | Hardeman | STP 2013(007) | 0043-02-070 | US 287 | $4,310,000.00 | 2 | ||
| Released | Hardin | NH 2013(053) | 0200-10-073 | US 69 | $2,077,912.14 | 1 | ||
| Released | Harris | NH 2013(063) | 0028-01-095 | BU 90-U | $3,500,000.00 | 1 | ||
| Released | Harris | CM 2013(081) | 0050-06-082 | US 290 | $5,818,311.11 | 1 | ||
| Released | Harris | NH 2013(082) | 0050-09-071 | US 290 | $94,494,160.52 | JUL | 2 | |
| Released | Harris | IM 6107(434) | 0271-17-154 | IH 610 | $444,325.00 | 2 | ||
| Released | Harris | BR 2006(741) | 0912-72-050 | CS | $1,231,284.59 | 2 | ||
| Released | Harris | NH 2013(064) | 1685-02-049 | FM 1960 | $586,176.50 | 1 | ||
| Released | Hemphill | STP 2013(003) | 0030-05-062 | US 83 | $3,580,741.80 | 2 | ||
| Released | Hidalgo | STP 2013(039)MM | 0669-01-043 | FM 681 | $10,678,191.00 | 1 | ||
| Released | Hidalgo | STP 2012(699)MM | 0698-03-084 | FM 88 | $2,567,652.00 | 2 | ||
| Released | Hidalgo | STP 1102(186)SRS | 0921-02-258 | CS | $3,056,105.25 | 2 | ||
| Released | Hopkins | BR 1102(533) | 0901-28-051 | CR | $729,000.00 | 1 | ||
| Released | Jasper | STP 2013(054)HES | 1275-01-037 | FM 1013 | $2,084,541.80 | 2 | ||
| Released | Jefferson | STP 2013(052) | 0028-06-074 | US 90 | $618,978.65 | 1 | ||
| Released | Johnson | STP 2013(013) | 2465-01-018 | FM 2280 | $839,102.00 | 2 | ||
| Released | Johnson | STP 2013(014) | 3414-01-010 | FM 3048 | $1,413,944.09 | 1 | ||
| Released | Karnes | STP 2013(037) | 0366-06-038 | SH 123 | $1,800,000.00 | 2 | ||
| Released | Karnes | BR 2013(038) | 2755-01-009 | FM 2724 | $2,760,000.00 | 1 | ||
| Released | Kerr | STP 2013(031) | 0142-08-006 | FM 394 | $1,100,000.00 | 1 | ||
| Released | Knox | BR 2013(008) | 0098-04-032 | SH 6 | $2,025,925.05 | 1 | ||
| OFF | Knox | STP 2013(138) | 0098-04-035 | SH 6 | -$132,803.00 | |||
| Released | Lampasas | STP 2012(006)HES | 1032-01-032 | FM 580 | $1,930,006.96 | 2 | ||
| Released | Lavaca | BR 2011(164) | 0913-29-041 | CR | $229,571.00 | 1 | ||
| Released | Lee | STP 2013(022)HES | 0334-05-030 | FM 141 | $1,920,527.20 | 2 | ||
| Released | Lee | NH 2013(024) | 0473-02-035 | SH 21 | $2,182,872.64 | 1 | ||
| Released | Limestone | STP 2012(453) | 0643-03-022 | FM 39 | $4,323,619.57 | 2 | ||
| OFF | Lubbock | STP 2013(019)MM | 0905-06-081 | CS | -$5,945,067.00 | |||
| Released | Martin | HP 2012(639) | 0380-07-024 | SH 349 | $4,928,199.45 | 2 | ||
| Released | Martin | STP 2012(640) | 0380-08-020 | SH 349 | $15,010,685.04 | 1 | ||
| Released | McLennan | BR 2012(686) | 0258-09-137 | SH 6 | $3,490,824.00 | 1 | ||
| Released | McLennan | STP 2013(018) | 2060-01-035 | FM 2113 | $3,039,107.44 | 1 | ||
| OFF | Medina | STP 2013(032) | 0421-08-032 | SH 173 | -$2,050,061.50 | 2 | ||
| Released | Medina | STP 2013(035) | 0848-01-038 | FM 462 | $2,464,727.48 | 1 | ||
| Released | Milam | BR 2010(948) | 0917-12-068 | CR | $454,833.59 | 1 | ||
| Off | Montgomery | IM 0451(344) | 0110-04-187 | IH 45 | -$500,000.00 | 2 | ||
| Released | Nacogdoches | STP 2013(067) | 0926-06-015 | FM 138 | $2,244,024.06 | 2 | ||
| Released | Nueces | FBD 2012(227) | 2263-02-091 | SH 361 | $431,974.00 | 2 | ||
| Released | Panola | NH 2013(049) | 0063-04-058 | US 59 | $1,370,000.00 | 2 | ||
| Released | Polk | STP 2012(085)HES | 3160-01-020 | FM 3126 | $1,600,049.02 | 1 | ||
| Released | Potter | STP 2013(004) | 0904-00-151 | VA | $500,000.00 | 1 | ||
| Released | Robertson | NH 2013(055) | 0049-06-075 | SH 6 | $381,180.06 | 2 | ||
| Released | Robertson | STP 2013(059)HRR | 0540-01-044 | FM 46 | $3,480,000.00 | 2 | ||
| Released | Robertson | BR 2010(949) | 0917-18-073 | CR | $454,233.83 | 1 | ||
| Released | Sabine | PLD 2013(065) | 0064-15-006 | FM 201 | $625,805.35 | 2 | ||
| Released | San Jacinto | STP 2013(066)G | 0177-13-006 | LP 424 | $108,633.00 | 1 | ||
| Released | Shelby | STP 2013(068) | 1879-01-022 | FM 2026 | $4,590,799.34 | 2 | ||
| Released | Smith | STP 2013(071) | 0910-00-092 | VA | $192,098.00 | 2 | ||
| Released | Somervell | STP 2013(012) | 0386-01-026 | SH 144 | $685,278.26 | 1 | ||
| Released | Stephens | STP 2012(005)HES | 0714-03-022 | FM 717 | $2,167,621.05 | 2 | ||
| Released | Tarrant | IM 0355(151) | 0014-16-255 | IH 35W | $132,983,648.00 | 2 | ||
| Released | Tarrant | IM 0304(096) | 1068-01-201 | IH 30 | $2,816,727.00 | 2 | ||
| Released | Tarrant | IM 0204(284) | 2374-05-077 | IH 20 | $3,394,279.00 | 1 | ||
| Released | Tom Green | STP 2013(020) | 0907-00-077 | VA | $1,269,127.80 | 1 | ||
| Released | Travis | NH 2013(026) | 0914-00-291 | VA | $500,000.40 | 1 | ||
| Released | Travis | NH 2013(027) | 0914-00-314 | VA | $3,003,519.65 | 2 | ||
| Released | Trinity | STP 2012(068)HES | 0475-08-011 | FM 230 | $1,286,409.72 | 2 | ||
| OFF | Uvalde | STP 2013(034) | 0595-01-008 | FM 1796 | -$2,234,400.48 | 2 | ||
| OFF | Uvalde | STP 2013(036) | 1168-02-015 | FM 1049 | -$2,592,693.50 | 1 | ||
| Released | Walker | STP 2013(060)HES | 0756-02-027 | FM 980 | $4,569,409.90 | 1 | ||
| Released | Washington | NH 2013(141) | 0114-10-091 | US 290 | $5,581,100.00 | 2 | ||
| Released | Wharton | STP 2013(073) | 0709-02-047 | FM 102 | $2,600,000.00 | 2 | ||
| Released | Williamson | HP 2013(023) | 0440-02-010 | SH 195 | $17,913,452.02 | 2 | ||
| 695,410,448.21 | ||||||||
| © 2011 Rapid Plans Company | ||||||||